Oct 1st 2012

Setup, pedestals, intercalibration

Run time run conditions comments
1 Sep 28th pedestals
11 11:20 torch test camera 4 – camera 2,3 not resp.
12 11:35 torch test camera 2,3 – camera 2,3 not resp.

Tuning of Gains (assuming factor 3 at SW level to account for multiple fibers in 0,1,2):

Camera Gain
0 600
1 690

Oct 5th 2012

Run time run conditions comments
15 14:30 pedestals
21 14:45 Laser tests
22 16:50 Laser tests
27 19:10 peds with only three cameras
28 19:10 signal with only three cameras – shutter on

Oct 9th 2012

Spectrometer chamber mounted under vacuum and lanex interposed for electron diagnostics

Run time run conditions comments
36 16:00 pedestals
40 16:20 ped with gain 1024, shutter 200
41 17:00 spari! B==0
42 18:00 scan gas jet B==0
43 18:00 scan gas jet B==0.45T (I=91A)
45 19:00 piedistallo con shutter 1
46 19:15 B==0 shutter 1
45 19:00 piedistallo con shutter 1 e gain 800
48 20:40 test (evt 160 buono)
51 20:45 torniamo a gain 1023
52 20:54 I=33A (B~0.15T) tanto: evt12, 14, 137,162,201

Oct 11th 2012

1) scan pedestals as a function of gain and shutter. Time base set to 20mus

2) align magnet with flange

3) correlate time stamps : spectr=19:10:30 –> monitoring=18:10:20

4) estimate rough calibration constants @ gain =900, shutter= 4 (x20mus) {1,1.4,0.7,1.3,0.5}

With B=0 nice collimated beam!

TODO:

A) redo ROI for camera 1,2
B) GUI:
    - debug spectrum plot
    - add possibility to subtract flat component 
    - correct for dead fibers
    - rebin (4 or 8)
C) estimate effect of lanex by removing it
D) screen spectrometer from direct laser
E) intercalibrate cameras offline (with electroluminescence)
F) integrate instructions for the camera readout into the manual
Run time run conditions comments
72 14:00 pedestals gain 1000 shut 4 (x20mus) cam03 non in DAQ; RMS~{4,1.5,1.5,-,3.5
73 14:00 pedestals gain 950 shut 4 (x20mus) cam03 non in DAQ; RMS~{4,1.5,1.5,-,3.5
74 14:00 pedestals gain 900 shut 4 (x20mus) cam03 non in DAQ; RMS~{3,1,1,-,2.5
75 14:00 pedestals gain 850 shut 4 (x20mus) cam03 non in DAQ; RMS~{2.4,1,1,-,2
78 16:00 pedestals gain 900 shut 6 (x20mus) RMS~{3.5,1.5,1.5,6,2.5}
83 17:45 pedestals gain 900 shut 10 (x20mus) RMS~{3,1.1,1.5,6,2.5}
84 17:50 spari (belli) scan posizione gas-jet Belli:29, 36
85 18:20 pedestals gain 900 shut 4 (x20mus) RMS~{3,1.1,0.9,3,2.5}
87 18:40 scan parabola with B=0
88 19:50 scan parabola with I=33A (B~0.15T)
92 00:00 scan parabola in y I=33A
93 00:30 scan parabola in x I=0
94 00:00 scan parabola in x I=33A
95 12:40 fix everything and run at I=33A (0.15T)
96 12:44 fix everything and run at I=0
97 12:48 fix everything and run at I=66A (0.3T)
98 12:51 fix everything and run at I=99A (0.45T)

Oct 12th 2012

New ROI file done (files calib2012Oct12). Run 101 pedestal run Run 102 and run 103 (skip first 100/200 events) runs done moving a lamp over the fibres to check mapping and intercalibration (0.8, 1.5, 1, 1.3, 1)

TO DO: redo wrapping of fibres especially those corresponding to maroc 0 and 4!

Oct 18th 2012

Shifted camera by 5mm

Rewrap fibers with thick aluminum

Run time run conditions comments
110 12:30 pedestals gain 900 shut 200 (x20mus) after rewrapping RMS~{1,0.5,0.5,0.6,1.1}
111 12:30 (light on) pedestals gain 900 shut 4 (x20mus) after rewrapping RMS~{1,0.5,0.5,0.6,1.1} – no change
112 12:30 turn off light gain 900 shut 4 (x20mus) RMS~{1,0.5,0.5,0.6,1.1}
strutture/lnf/da/plasmonx/lpa/spectrometer/v1commissioning/oct2012.txt · Last modified: 2012/10/18 10:55 by faccini@infn.it